What Actually Holds Up a Demolition Permit

Demo Dynasty Team 6 min read
What Actually Holds Up a Demolition Permit
Demo Dynasty

Owners planning a demolition tend to think of the permit as a step with a duration. In practice it is a gate, and what holds it closed is nearly always the prerequisites rather than the review.

The three items that gate it

The asbestos survey. Almost every jurisdiction requires a survey by a qualified inspector before a demolition permit is issued, on essentially any commercial or industrial building regardless of age. Where the survey finds regulated material, abatement has to be complete and documented before demolition, which adds its own duration.

Utility disconnection documentation. Not a statement that it has been arranged — proof from each utility that the service is disconnected. Electric, gas, water, sewer, and depending on the jurisdiction, telecom and fire service. Each runs on its own schedule and none of them accelerate for your deadline.

NESHAP notification. Where applicable, notification to the appropriate agency with a required advance period before work begins. Miss the notification and the clock starts over regardless of everything else being ready.

Every one of those can be started the day the demolition decision is made, and every one of them is routinely started weeks later.

What else is commonly required

  • A site plan showing the structure, the property lines and the work area.
  • A demolition plan describing the method and sequence.
  • Contractor licensing and insurance documentation.
  • A dust and erosion control plan.
  • Traffic control plans where public right of way is affected.
  • Historic review, in designated districts.
  • Confirmation the structure is unoccupied, and in some jurisdictions, evidence of rodent abatement.

Each is straightforward. Missing any of them means a resubmission, and a resubmission means going back into the queue rather than being reviewed on the spot.

Jurisdiction differences are real

Requirements and turnaround vary considerably between counties and municipalities, and buildings near jurisdictional lines cause genuine confusion about which office to file with. A property inside city limits usually goes to the city rather than the county.

The practical approach is confirming the requirements with the specific office before assembling the submission, rather than assuming the process matches the last project.

Historic review is the long one

In designated historic districts, and for structures of a certain age in some jurisdictions, there may be a review process with its own board, its own meeting schedule and its own criteria. That process can add months and it can result in denial.

Establishing whether a property is subject to historic review is a due diligence item, not a permitting item, and finding out late is one of the more expensive discoveries in this business.

Complete beats fast

A submission with everything included is reviewed once. A submission missing an item is returned, corrected and resubmitted, which in a busy office can double the elapsed time for a single missing document.

That is why we assemble the full package before filing rather than submitting early and supplementing.

Who does what

On our projects we pull the permit, coordinate the survey, manage the utility disconnection requests and handle the notifications, because we know what each jurisdiction requires and how long each utility takes.

What we need from an owner is the decision made early enough, access for the survey, and any records of what services and structures exist on the parcel — particularly the ones that are not obvious from the outside.

The single most useful thing an owner can do is start the survey and the utility requests on day one, before contractor selection is finalised. It costs nothing and it is the difference between a permit that is ready when you are and one that holds up the whole project.